✓Building permit for roof mounting and structural loads
✓Electrical permit for all wiring and inverter connections
✓Utility interconnection approval from local electricity distributor
✓Net metering agreement may be required with your utility
✅ Exemptions
No exemptions — all grid-tied solar installations require permits.
Required Inspections
1
Structural/mounting inspection
2
Electrical inspection
3
Utility interconnection inspection
How to Apply in Kelowna
1
Check if you need a permit
Review the requirements above. For a solar panel installation, a permit is always required.
2
Prepare your documents
Gather drawings, site plans, and specifications. For larger projects, you may need drawings stamped by a licensed engineer or architect.
3
Submit to Building Services
Apply online at https://kelowna.ca or visit in person at 1435 Water St, Kelowna, BC V1Y 1J4.
4
Wait for approval
Kelowna typically processes solar panel installation permits in 2–6 weeks. You will receive a permit number when approved.
5
Post permit & book inspections
Post your permit on site. Book required inspections at each stage — do not cover work before it is inspected.
FAQs — Solar Panel Installation Permit in Kelowna
How much does a solar panel installation permit cost in Kelowna?
Solar Panel Installation permit fees in Kelowna typically range from $150–$600. Fees are usually based on the estimated project value. Contact Building Services at 250-469-8630 to get an exact quote for your project.
Can I do my own solar panel installation without a contractor?
Homeowners can often pull their own permits for work on their primary residence. However, electrical and plumbing work typically requires a licensed trade. Check with Building Services for specific rules.
What happens if I skip the permit?
Unpermitted work can result in fines, orders to undo completed work, problems with home insurance claims, and difficulty selling your home. It is always worth the time to verify permit requirements.